1.When 8–13 of oversize stones are laid in a concrete block, the difference between the temperatures of the concrete mix and the stone being 4–6°C, the maximum temperatures for exothermal heating of the concrete fall by 2–6°C.2.Laying of stones at −14°C in concrete mix at 6–7°C does not lead to freezing of the concrete mix at the stone-mix contact provided that the concreting is performed under a heated canvas shelter.3.When 8–13 of stone is laid in the block and when the temperature difference between the concrete mix and the stone is 4–21°C, during the stage of exothermic heating the concrete around the stone is compressed. There is a tendency for the compressive deformations to decrease as the stone content of the concrete increases.4.During cooling of stone-concrete blocks, the stress state of the concrete surrounding a stone is mainly governed by the overall thermal stress state of the blocks.5.Field investigations of the temperatures and thermal stress states of stone-concrete masonry show that it is possible and advantageous to lay oversize stones (even if their temperatures are 15–20°C below the temperature of the concrete mix) in the inter
机译:1.当8-13%的超大石材铺设在混凝土砌块中时,混凝土混合物和石材之间的温度差为4-6°C,混凝土放热加热的最高温度下降2-6°C.2.在-14°C的混凝土混合物中,在6-7°C的混凝土混合物中铺设石头不会导致混凝土混合物在石材混合料接触处冻结,前提是混凝土浇筑是在加热帆布遮蔽物.3.当8-13%的石材铺设在砌块中时,当混凝土混合料与石材之间的温差为4-21°C时,在放热加热阶段,石材周围的混凝土被压缩。4.在石材-混凝土砌块冷却过程中,石材周围的混凝土应力状态主要受砌块的整体热应力状态控制.5.对石材-混凝土砌体的温度和热应力状态的现场调查表明,铺设超大尺寸的石材是可能的,也是有利的(即使它们的温度低于混凝土混合物的温度)在内部

著录项

相似文献

  • 外文文献
  • 中文文献
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号